Location

McKinney, Texas

BRIDGE - CAMBRIDGE CROSSING

Bridge at Craig Ranch – Master-Planned Residential Community

Request

The customer desired an appealing bridge design that would not only satisfy the necessary FEMA waterway regulations, but also enhance the overall aesthetic of the development.

Solution

Speed Fab Crete crafted a sophisticated five-cell arch structure complete with spacious medians and expansive sidewalks on either side.

Results

The bridge was fabricated in 3 months, swiftly installed within 2 weeks, and featured walls adorned with natural stone and distinctive lighting elements.

  • BRIDGE - CAMBRIDGE CROSSING

Experience the trust others have found – it’s your turn now.